Project title: Supply of water to the great area of city of Rhodes – water supply pipe and water filtering installations from Gadoura Dam
Project owner / Employer: Ministry of infrastructures / AEGEK
Kind of services: Basic design – Final design – Detail design
Duration: 1998 – 2000 / 2005 – 2006 / 2007 – 2009
Object of supply of services: The object of the primary contract was the elaboration of the final design of the water supply network from Gadoura dam to Asgouros tank, the writing of tender documents as well as the elaboration of preliminary design of the water treatment installations (treatment plant), while in continuance the final design (detail design level) of water treatment installations and the final design (detail design level) of the water supply network were elaborated